Find how much soil comes out of a hole, how much it weighs and how many truck or skip loads it takes.
Your excavation
Soil takes more room once it is dug. The calculator uses the bank and loose densities that Caterpillar publishes for common soils.
Size and soil
Average depth below the ground.
For several equal holes or trench sections.
Weights vary with moisture and stones; ask the haulier if in doubt.
Truck or skip
What the truck or skip holds, heaped soil. Leave empty to skip.
Weight limit of the truck or skip. Optional.
Add this calculator to your website
Free for any website: paste this code where the calculator should appear. It keeps itself up to date, fits its height to the content and links back to the full page with the explanations.
Cara menggunakan
- 01Enter the length, width and average depth of the pit, trench or area you dig out. For several equal holes, enter the number.
- 02Choose the soil that comes closest to yours.
- 03Enter what one truck or skip holds, and its weight limit if you know it.
- 04Read the loose volume to haul away, the weight and the number of loads.
Cara menghitung
Soil in the ground is packed tight. Once it is dug, air gets between the grains and the same soil takes more room. Earthmovers call the two states bank volume and loose volume. The weight stays the same, so the ratio of the two densities gives the swell.
- In the ground
- V_bank = length × width × depth × holes
- Weight
- m = V_bank × bank density
- Dug soil
- V_loose = m / loose density
- Loads
- max(ceil(V_loose / load volume), ceil(m / payload))
The densities come from the earthwork reference tables published by Caterpillar. Dry packed earth weighs 1,900 kg/m³ in the ground and 1,510 kg/m³ dug, a swell of about 26 %. Topsoil swells most of the soils listed, about 44 %; gravel and sand about 12 %.
Weights change with moisture, stones and compaction, so treat the numbers as a planning value. Wet clay is among the heaviest soils; with it a truck often reaches its weight limit before it is full.
Soil put back and compacted takes less room than loose soil, sometimes less than it did in the ground. The calculator does not count backfill, because that depends on how well it is compacted.
Contoh perhitungan
Digging out a 10 × 8 m area 40 cm deep in dry packed earth, 10 m³ truck
- In the ground: 10 × 8 × 0.4 = 32 m³.
- Weight: 32 × 1,900 = 60.8 t.
- Dug: 60,800 / 1,510 = 40.3 m³, about 26 % more.
- Loads: 40.3 / 10 = 4.03, so 5 truck loads, not the 4 the hole size suggests.
Tips memesan bahan
Ask for the payload
Skips and trucks have a weight limit as well as a volume. With heavy wet clay, enter both to see which one limits the loads.
Keep the topsoil apart
Strip the topsoil first and pile it separately. It is worth keeping for the garden, and mixed with subsoil it is spoiled.
Measure the depth at several points
On sloping ground, measure the depth at the corners and the middle and use the average.
Check before you dig
Ask for the plans of underground cables and pipes before digging, and keep trench sides safe: deep trenches need shoring or battered sides.
Kesalahan umum
- Ordering skips by the size of the hole and running out of space.
- Overloading a skip with heavy soil. The weight limit is often reached before the skip is full.
- Forgetting that a trench for a footing is wider than the footing itself.
- Counting on the dug soil to refill the hole exactly. Compacted soil takes less room.
Tanya jawab
How much does excavated soil expand?
Dry packed earth by about 26 %, clay by 20 to 25 %, sand and gravel by about 12 %, topsoil by over 40 %, based on the Caterpillar density tables.
How much does a cubic metre of soil weigh?
In the ground, dry packed earth about 1.9 t, loam about 1.5 t, wet clay about 2.1 t. Dug, the same volume weighs less because it holds air.
How many skips do I need?
Loose volume divided by the skip volume, rounded up. Check the weight too: heavy soil can reach the limit first.
Can I use the dug soil as backfill?
Often yes, but compacted soil takes less room than loose soil. Plan the backfill with the supplier or by trial.
Kalkulator terkait
Sumber
- [1]Earthwork volumes reference tables: common materials loose and bank. Caterpillar. Bank and loose densities (kg/m³) and load factors: clay natural bed 2020/1660, clay dry 1840/1480, clay wet 2080/1660, clay & gravel dry 1660/1420, earth dry packed 1900/1510, earth loam 1540/1250, gravel dry 1690/1510, sand dry 1600/1420, sand damp 1900/1690, sand & gravel dry 1930/1720, topsoil 1370/950. Values vary with moisture, grain size and compaction.. Diperiksa 11 November 2026
Rumus dan sumber terakhir diperiksa pada 11 November 2026. Cara kami menghitung